General Assumptions

Id Activity Value Uom Description Remarks Source
1 Process Isolation 0.25 h/conn. Time needed to close a SBB and to check proper isolation expert judgment
2 Process Isolation 0.50 h/conn. Time needed to close a DBB and to check proper isolation expert judgment
3 Depressurization 0.50 h Time needed to reach atmospheric pressure by opening BDV and discharging to flare expert judgment
4 Cool down See dedicated table expert judgment
5 Electrical Isolation 0.25 h Time needed to locate and disconnect the circuit breaker and to verify isolation in field according to HSE procedures expert judgment
6 Draining 0.50 h Time needed to open connections to drain system (or to connect temporary lines) expert judgment
7 Draining 2.50 m/s Liquid velocity in the draining line expert judgment
8 Purging 0.50 h Time needed to connect the nitrogen generator expert judgment
9 Purging 2.00 bar Pressurization pressure (applicable to purging by pressurization/depr. cycles) expert judgment
10 Purging 1.00 bar Discharge pressure (applicable to purging by pressurization/depr. cycles) expert judgment
11 Purging 1,400.00 Sm3/h Nitrogen generator flow rate TO BE DEFINED BASED ON PROJECT PROJECT SOURCE
12 Purging 3.00 n/a Sweeping factor expert judgment
13 Blinding 0.50 h/conn. Time needed to apply/remove positive isolation devices (i.e. spectacles, blind flanges, spools) expert judgment
14 Ventilation 0.50 h Time needed to open a manway expert judgment
15 Ventilation 1.00 min/m3 Time needed for ventilation expert judgment
16 Ventilation 24.00 h Maximum ventilation time expert judgment
17 Washing See dedicated table ENI Std. 20560_430_rev02
18 Item Removal See dedicated table expert judgment
19 Reinstalling 0.50 h/conn. Time needed to remove positive isolation devices or to reinstall spools expert judgment
20 Reinstalling 0.25 h/conn. Time needed to open isolation valves expert judgment