<Table name="General Assumptions">
    <Row>
        <Id>1</Id>
        <Activity>Process Isolation</Activity>
        <Value>0.25</Value>
        <Uom>h/conn.</Uom>
        <Description>Time needed to close a SBB and to check proper isolation</Description>
        <Remarks></Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>2</Id>
        <Activity>Process Isolation</Activity>
        <Value>0.50</Value>
        <Uom>h/conn.</Uom>
        <Description>Time needed to close a DBB and to check proper isolation</Description>
        <Remarks></Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>3</Id>
        <Activity>Depressurization</Activity>
        <Value>0.50</Value>
        <Uom>h</Uom>
        <Description>Time needed to reach atmospheric  pressure by opening BDV and discharging to flare</Description>
        <Remarks></Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>4</Id>
        <Activity>Cool down</Activity>
        <Value></Value>
        <Uom></Uom>
        <Description>See dedicated table</Description>
        <Remarks></Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>5</Id>
        <Activity>Electrical Isolation</Activity>
        <Value>0.25</Value>
        <Uom>h</Uom>
        <Description>Time needed to locate and disconnect the circuit breaker and to verify isolation in field according to HSE procedures</Description>
        <Remarks></Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>6</Id>
        <Activity>Draining</Activity>
        <Value>0.50</Value>
        <Uom>h</Uom>
        <Description>Time needed to open connections to drain system (or to connect temporary lines)</Description>
        <Remarks></Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>7</Id>
        <Activity>Draining</Activity>
        <Value>2.50</Value>
        <Uom>m/s</Uom>
        <Description>Liquid velocity in the draining line</Description>
        <Remarks></Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>8</Id>
        <Activity>Purging</Activity>
        <Value>0.50</Value>
        <Uom>h</Uom>
        <Description>Time needed to connect the nitrogen generator</Description>
        <Remarks></Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>9</Id>
        <Activity>Purging</Activity>
        <Value>2.00</Value>
        <Uom>bar</Uom>
        <Description>Pressurization pressure (applicable to purging by pressurization/depr. cycles)</Description>
        <Remarks></Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>10</Id>
        <Activity>Purging</Activity>
        <Value>1.00</Value>
        <Uom>bar</Uom>
        <Description>Discharge pressure (applicable to purging by pressurization/depr. cycles)</Description>
        <Remarks></Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>11</Id>
        <Activity>Purging</Activity>
        <Value>1,400.00</Value>
        <Uom>Sm3/h</Uom>
        <Description>Nitrogen generator flow rate</Description>
        <Remarks>TO BE DEFINED BASED ON PROJECT</Remarks>
        <Source>PROJECT SOURCE</Source>
    </Row>
    <Row>
        <Id>12</Id>
        <Activity>Purging</Activity>
        <Value>3.00</Value>
        <Uom>n/a</Uom>
        <Description>Sweeping factor</Description>
        <Remarks></Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>13</Id>
        <Activity>Blinding</Activity>
        <Value>0.50</Value>
        <Uom>h/conn.</Uom>
        <Description>Time needed to apply/remove positive isolation devices (i.e. spectacles, blind flanges, spools)</Description>
        <Remarks></Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>14</Id>
        <Activity>Ventilation</Activity>
        <Value>0.50</Value>
        <Uom>h</Uom>
        <Description>Time needed to open a manway</Description>
        <Remarks></Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>15</Id>
        <Activity>Ventilation</Activity>
        <Value>1.00</Value>
        <Uom>min/m3</Uom>
        <Description>Time needed for ventilation</Description>
        <Remarks></Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>16</Id>
        <Activity>Ventilation</Activity>
        <Value>24.00</Value>
        <Uom>h</Uom>
        <Description>Maximum ventilation time</Description>
        <Remarks></Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>17</Id>
        <Activity>Washing</Activity>
        <Value></Value>
        <Uom></Uom>
        <Description>See dedicated table</Description>
        <Remarks></Remarks>
        <Source>ENI Std. 20560_430_rev02</Source>
    </Row>
    <Row>
        <Id>18</Id>
        <Activity>Item Removal</Activity>
        <Value></Value>
        <Uom></Uom>
        <Description>See dedicated table</Description>
        <Remarks></Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>19</Id>
        <Activity>Reinstalling</Activity>
        <Value>0.50</Value>
        <Uom>h/conn.</Uom>
        <Description>Time needed to remove positive isolation devices or to reinstall spools</Description>
        <Remarks></Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>20</Id>
        <Activity>Reinstalling</Activity>
        <Value>0.25</Value>
        <Uom>h/conn.</Uom>
        <Description>Time needed to open isolation valves</Description>
        <Remarks></Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>21</Id>
        <Activity>Reinstalling</Activity>
        <Value></Value>
        <Uom></Uom>
        <Description>Time needed to restore other mechanical connections: see dedicated table</Description>
        <Remarks></Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>22</Id>
        <Activity>Leak test</Activity>
        <Value>0.50</Value>
        <Uom>h</Uom>
        <Description>Time needed to connect the high pressure nitrogen generator</Description>
        <Remarks></Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>23</Id>
        <Activity>Leak test</Activity>
        <Value>1.10</Value>
        <Uom></Uom>
        <Description>Leak test pressure to operating pressure ratio</Description>
        <Remarks></Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>24</Id>
        <Activity>Leak test</Activity>
        <Value>1,400.00</Value>
        <Uom>Sm3/h</Uom>
        <Description>High pressure nitrogen flow rate</Description>
        <Remarks>TO BE DEFINED BASED ON PROJECT</Remarks>
        <Source>PROJECT SOURCE</Source>
    </Row>
    <Row>
        <Id>25</Id>
        <Activity>Leak test</Activity>
        <Value>0.25</Value>
        <Uom>h/conn.</Uom>
        <Description>Time needed to check each flange for leaks after the test pressure is achieved</Description>
        <Remarks></Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>26</Id>
        <Activity>Air Removal</Activity>
        <Value>0.50</Value>
        <Uom>h</Uom>
        <Description>Time needed to connect the nitrogen generator</Description>
        <Remarks></Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>27</Id>
        <Activity>Air Removal</Activity>
        <Value>0.21</Value>
        <Uom></Uom>
        <Description>Initial oxygen concentration (in case leak test has not been performed)</Description>
        <Remarks></Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>28</Id>
        <Activity>Air Removal</Activity>
        <Value>0.03</Value>
        <Uom></Uom>
        <Description>Target oxygen concentration</Description>
        <Remarks></Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>29</Id>
        <Activity>Air Removal</Activity>
        <Value>2.00</Value>
        <Uom></Uom>
        <Description>Pressurization pressure (applicable to purging by pressurization/depr. cycles)</Description>
        <Remarks>Assumed equal to Purging</Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>30</Id>
        <Activity>Air Removal</Activity>
        <Value>1.00</Value>
        <Uom></Uom>
        <Description>Discharge pressure (applicable to purging by pressurization/depr. cycles)</Description>
        <Remarks>Assumed equal to Purging</Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>31</Id>
        <Activity>Air Removal</Activity>
        <Value>1,400.00</Value>
        <Uom></Uom>
        <Description>Nitrogen generator flow rate</Description>
        <Remarks>Assumed equal to Purging</Remarks>
        <Source>expert judgment 342101BPST02508 34210ABPRV02054</Source>
    </Row>
    <Row>
        <Id>32</Id>
        <Activity>Commissioning & Start up</Activity>
        <Value>1.00</Value>
        <Uom>h</Uom>
        <Description>Temperature restoring time</Description>
        <Remarks></Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>33</Id>
        <Activity>Commissioning & Start up</Activity>
        <Value>0.50</Value>
        <Uom>h</Uom>
        <Description>Pressure restoring time</Description>
        <Remarks>Assumed equal to Depressurization time</Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>34</Id>
        <Activity>Commissioning & Start up</Activity>
        <Value></Value>
        <Uom></Uom>
        <Description>Level restoring time</Description>
        <Remarks>Assumed equal to Draining time</Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>35</Id>
        <Activity></Activity>
        <Value>2.00</Value>
        <Uom></Uom>
        <Description>Maximum numbers of crews working in parallel for isolation/blinding</Description>
        <Remarks></Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>36</Id>
        <Activity></Activity>
        <Value>0.80</Value>
        <Uom></Uom>
        <Description>Efficiency of maintenance crew</Description>
        <Remarks>Not applied to essentially labor-free activities (i.e. Cool down and Ventilation)</Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>37</Id>
        <Activity>Item conveyance to workshop</Activity>
        <Value>1.00</Value>
        <Uom>h</Uom>
        <Description>Loading / Unloading</Description>
        <Remarks></Remarks>
        <Source>expert judgment</Source>
    </Row>
    <Row>
        <Id>38</Id>
        <Activity>Item conveyance to workshop</Activity>
        <Value>1.00</Value>
        <Uom>h</Uom>
        <Description>Travel to WS</Description>
        <Remarks></Remarks>
        <Source>expert judgment</Source>
    </Row>
</Table>